PCG is teamed with KAI Design & Build to provide construction management services to the St. Louis Metropolitan Sewer District for Tanks/Treatment/and Pump Station Facilities projects. PCG is reviewing estimates of probable construction costs prepared by the project designers at the 30%, 60%, 90% and 100% design phases. After the projects go into construction, PCG is preparing independent change order estimates for comparison with costs received from the General Contractors. PCG is also reviewing Contractors submitted baseline schedules and performing schedule analysis of the monthly schedule submittals.